Question 1:

You are managing a project that is in process. A large and unexpected problem occurs that will cause a delay in the schedule in excess of the contingency schedule for the project. What should you do?

A - Look at other tasks in the schedule and see which ones should be reduced to allow time for this problem to be worked
B - Reduce testing on the completed tasks
C - Require mandatory overtime for the project team
D - Speak to the stakeholders about getting additional time and budget for the project