Question 1:
You are a project manager working on a project to market a new product. The deliverable of the project have been established, and the project work has begun. A contract to deliver the deliverable has been signed. The customer who has signed the contract has telephoned you to request additional work to be done on the project. This work will affect the budget but not the schedule of the project. This project has a high priority with your company. What should you so next?